Rule 136 of The General Financial Rules 2017 Conditions for Commencement of Works

Rule 136 of The General Financial Rules 2017 Conditions for Commencement of Works

Original Rule Text

Rule 136 (1) No works shall be commenced or liability incurred in connection with it until:(i) Administrative approval has been obtained from the appropriate authority in each case.(ii) Sanction to incur expenditure has been obtained from the competent authority.(iii) A properly detailed design has been sanctioned; while by designing the projects etc, principles of Life Cycle cost may also be considered.(iv) Estimates containing the detailed specifications and quantities of various items have been prepared on the basis of the Schedule of Rates maintained by CPWD or other Public Works Organisations and sanctioned.(v) Funds to cover the charges during the year have been provided by competent authority.(vi) Tenders invited and processed in accordance with rules.(vii) a Work Order issued.Rule 136 (2) On grounds of urgency or otherwise, if it becomes necessary to carry out a work or incur a liability under circumstances when the provisions set out under sub rule 1 of rule 136 cannot be complied with, the concerned executive officer may do so on his own judgement and responsibility. Simultaneously, he should initiate action to obtain approval from the competent authority and also to intimate the concerned Accounts Officer.Rule 136 (3) Any development of a project considered necessary while a work is in progress, which is not contingent on the execution of work as first sanctioned, shall have to be covered by a supplementary estimate.

Visual Summary

Admin Approval

Essential before starting any work.

Expenditure Sanction

Funds must be approved by competent authority.

Design & Estimates

Detailed plans and cost estimates are mandatory.

Executive Summary

Rule 136 of The General Financial Rules, 2017, establishes the foundational requirements for commencing any government work or incurring related liabilities. It mandates administrative approval, expenditure sanction, detailed design, sanctioned estimates, fund provision, tender processing, and a formal work order. In urgent situations where these conditions cannot be fully met, an executive officer may proceed on their own judgment but must immediately seek competent authority approval and inform the Accounts Officer. Any project development not part of the original sanction requires a supplementary estimate.

In-Depth Analysis of the Rule

Rule 136 serves as a critical control mechanism within government financial management, ensuring that public works are initiated only after thorough planning, approval, and resource allocation. This rule aims to prevent arbitrary expenditure, promote financial discipline, and ensure accountability in project execution.

Breakdown of the Rule
  • Administrative Approval (136(1)(i)): This is the initial green light, confirming the necessity and desirability of the work from an administrative perspective.
  • Expenditure Sanction (136(1)(ii)): A separate sanction is required to incur the actual financial outlay, ensuring funds are available and approved for the specific purpose.
  • Detailed Design & Life Cycle Cost (136(1)(iii)): Emphasizes meticulous planning, including detailed designs and consideration of the project’s total cost over its entire lifespan, not just initial construction.
  • Sanctioned Estimates (136(1)(iv)): Requires precise cost estimates based on standard rates, ensuring financial realism and preventing cost overruns.
  • Fund Provision (136(1)(v)): Confirms that adequate funds are allocated in the budget for the current year’s charges, linking project initiation directly to budgetary availability.
  • Tender Process (136(1)(vi)): Mandates competitive tendering, ensuring transparency, fairness, and value for money in selecting contractors.
  • Work Order (136(1)(vii)): The final formal instruction to commence work, issued after all preceding conditions are met.
  • Urgency Clause (136(2)): Provides flexibility for urgent situations, allowing executive officers to proceed on their own judgment, but with an immediate obligation to seek retrospective approval and inform the Accounts Officer.
  • Supplementary Estimates (136(3)): Ensures financial control over project modifications, requiring additional estimates for any developments not part of the original sanctioned work.
Practical Example

Imagine a Ministry needs to construct a new research facility. Before breaking ground, Rule 136 dictates a series of steps. First, the Ministry must obtain administrative approval for the project. Next, a separate sanction for the expenditure must be secured. Engineers then prepare detailed designs, considering the facility’s life cycle costs. Based on these designs, precise estimates are drawn up and sanctioned. Funds for the current year’s construction must be explicitly provided in the budget. Tenders are then invited from qualified contractors, and a formal work order is issued to the selected firm. If, during construction, an urgent, unforeseen structural modification becomes necessary (e.g., due to a newly discovered geological fault), the executive officer can authorize it immediately under Rule 136(2) but must promptly seek formal approval and notify the Accounts Officer. Any significant addition to the facility not in the original plan would require a supplementary estimate under Rule 136(3).

Related Provisions

Understanding Rule 136 is enhanced by considering its connections to other financial regulations:

Learning Aids

Mnemonics
  • Administrative Approval, Expenditure Sanction, Detailed Design, Estimates Sanctioned, Funds Provided, Tenders Invited, Work Order. (AAESDESTIWO – “Always Approve Every Single Detailed Estimate, Sanction Funds, Tender Invitations, Work Orders”)
Process Flowchart

StartAdministrative ApprovalExpenditure SanctionDetailed Design SanctionedEstimates Prepared/SanctionedFunds ProvidedTenders Invited/ProcessedWork Order IssuedWork CommencesUrgent Need?(Rule 136(2))YesExecutive Officer ActsSeek Approval/Intimate AONoProject Development?(Rule 136(3))YesSupplementary EstimateNoEnd

Multiple Choice Questions

1. What is the first mandatory step before commencing any work under Rule 136 of the General Financial Rules, 2017?

  • A) Tenders invited and processed.
  • B) Administrative approval obtained.
  • C) Funds to cover charges provided.
  • D) A Work Order issued.
Show Answer

Correct Answer: B) Administrative approval obtained.

2. According to Rule 136 (1) of the General Financial Rules, 2017, which of the following is not a prerequisite for commencing work?

  • A) Sanction to incur expenditure.
  • B) Detailed design sanctioned.
  • C) Post-completion audit report.
  • D) Funds to cover charges provided.
Show Answer

Correct Answer: C) Post-completion audit report.

3. Under Rule 136 (2) of the General Financial Rules, 2017, if an urgent work must be carried out without fulfilling all prerequisites, what must the executive officer do simultaneously?

  • A) Halt all other ongoing projects.
  • B) Obtain approval from the competent authority and intimate the Accounts Officer.
  • C) Immediately secure supplementary funding.
  • D) Redesign the entire project.
Show Answer

Correct Answer: B) Obtain approval from the competent authority and intimate the Accounts Officer.

4. Rule 136 (3) of the General Financial Rules, 2017, states that any development of a project considered necessary while a work is in progress, and not contingent on the first sanctioned execution, requires what?

  • A) A new administrative approval.
  • B) A supplementary estimate.
  • C) A revised work order.
  • D) Direct approval from the Ministry of Finance.
Show Answer

Correct Answer: B) A supplementary estimate.

5. When designing projects, Rule 136 (1) (iii) of the General Financial Rules, 2017, suggests considering the principles of:

  • A) Short-term profitability.
  • B) Immediate cost recovery.
  • C) Life Cycle cost.
  • D) Minimal resource allocation.
Show Answer

Correct Answer: C) Life Cycle cost.

Frequently Asked Questions

What is the primary purpose of Rule 136 of The General Financial Rules, 2017?

The primary purpose is to establish a robust framework of prerequisites—including administrative approval, expenditure sanction, detailed design, and fund provision—that must be met before any government work can commence or related liabilities incurred, ensuring financial propriety and accountability.

Can a government work be started without all the conditions of Rule 136 (1) of The General Financial Rules, 2017, being met?

Yes, Rule 136 (2) allows an executive officer to proceed with urgent work on their own judgment if the conditions cannot be complied with, but they must simultaneously initiate action to obtain approval from the competent authority and inform the Accounts Officer.

What happens if a project needs additional work not covered by the original sanction under Rule 136 of The General Financial Rules, 2017?

Rule 136 (3) specifies that any such development, if not contingent on the execution of the work as first sanctioned, must be covered by a supplementary estimate.

Key Takeaways

  • Rule 136 mandates a multi-stage approval process for all government works, emphasizing administrative, financial, and technical clearances.
  • It requires detailed planning, including design and cost estimates, and ensures budgetary allocation before work commences.
  • The rule provides an exception for urgent situations, allowing work to start with immediate retrospective approval and notification to the Accounts Officer.
  • Any significant changes or additions to a project during its progress necessitate a supplementary estimate to maintain financial control.

Conclusion

Rule 136 of The General Financial Rules, 2017, is a cornerstone of prudent financial management in government works. By establishing clear prerequisites and a mechanism for urgent action with accountability, it ensures that public funds are utilized efficiently, transparently, and in accordance with approved plans, thereby safeguarding public interest and promoting sound project governance.