Section 53 of the Indian Contract Act, 1872 – Liability of party preventing event on which the contract is to take effect

Home › The Indian Contract Act, 1872 › Chapter IV – Chapter iv

Section 53: Liability of party preventing event on which the contract is to take effect

When a contract contains reciprocal promises, and one party to the contract prevents the other from performing his promise, the contract becomes voidable at the option of the party so prevented; and he is entitled to compensation from the other party for any loss which he may sustain in consequence of the nonperformance of the contract. Illustration A and B contract that B shall execute certain work for A for a thousand rupees. B is ready and willing to execute the work accordingly, but A prevents him from doing so. The contract is voidable at the option of B; and, if he elects to rescind it, he is entitled to recover from A compensation for any loss which he has incurred by its non-performance.

Source: official text of The Indian Contract Act, 1872 as published on India Code (PDF). All sections of the Indian Contract Act, 1872.